某项目经理想针对计划项目的实际结果编写报告,他会采用:( )

A.趋势报告

B.预测报告

C.状态报告

D.变量报告

正确答案:D


143 Forecasting human resource requirements necessitates making predictions about both the supply and demand of human resources. Which of the following is not a method used to forecast the demand for human resources?

A. Delphi Method

B. Regression Analysis

C. PERT Charts

D. Staffing Tables

E. Time Series Analysis

正确答案:C


24 The project charter is prepared in which scope management process?

A. Initiation

B. Scope planning

C. Scope Definition

D. Scope change control

E. Scope verification

正确答案:A


在一个环境改造项目中,以下哪项是一个增值变更的范例?

A、 由于政府规定经过修订,需要重新提交设计

B、 利用按照原来定的范围不可获取的可以降低成本的技术

C、 合用材料清单定义项目的整个范围,包括所有的组件和子组件

D、 修正系统设计中遗漏的但应该有的特征

正确答案:B


● Project alternatives are examined during the _____ phase of the project

A conceptual

B finish

C development

D implementation

E A and C

正确答案:E


现在已经落实了项目预算,然而在预算或项目范围中却有些工作没有计划到,在哪儿可以找到执行这些新发现的要作的资金? ( )

A.应急储备

B.项目利润

C.管理储备

D.放弃资金

正确答案:C


Sally是项目经理和两个组员解决一个冲突。 其中一方, Bill已经退出。 另一个,Kathleen试图采取折衷的办法,问题解决得很慢。由于问题得不到解决, 为快要达到的一个里程碑造成了很大的负面影响。Sally 召集两人正视问题, 但是, 两个人都不配合他解决问题。 Sally 最终听取了两方面的意见后作出决定。 Bill的形势优于Kathleen。 Sally最终采取那种方式解决问题?

a. 折衷

b. 冲突

c. 强迫

d. 缓和

e. b 和c

正确答案:A
a  [当选择项目组织结构时必须考虑很多因素以保证能覆盖所有或有费用。例如,项目规格及工期,项目经理的经验,高级管理的支援程度,项目所出的位置,可用资源以及是否有常规经验,客户关注点和差异,项目的类型等。为将所有这些项目包括在内,项目管理就是将它们结合在一个项目中的一种手段]


项目管理师考试题免费下载8篇 第2篇


你最后完成了一个涉及当地发电站有害废物处理的大型环境补救项目。你们的客户验收了你们的工作,你们公司也得了付款。项目正式结束有 6个多星期了。现在你从事的新项目正好还是在那个相同的当地的发电站进行。

在实施新项目的时候,你发现前一个已交付使用的项目的处理系统可能存着缺陷。你重新查看了原来项目的图纸,发现它的确实是不完善的。但没有人认同你的担心。而你认为在5年之内也不会出现明显的问题。在这种情况下,你应该

a. 什么也不要做,因为这个项目已经结束了,而且客户也经他们自己的独立检查将项 目验收通过了

b. 同时以口头和书面两种形式向你的主管通告这种情况,并找别人来的发现

c. 直接同客户取得联系,通知他们这个潜在的问题以修改你们的合同来纠正问题

d. 在未来的项目中马列上完善你们的质量保证和项目回顾系统

正确答案:A
a.  同时以口头和书面两种形式向你的主管通告这种情况,并找别人来确认你的发现 在这种情况下,这个己交付使用的、已经完成并通过客户验收的项目只是存在出现问题的潜在可能性,这一点也尚未被证实。尽管这个项目已经结束了,但仍旧要求采取进一步的行动。在你作为一名项目管理业务方面的专业人士参与工作的时候,个人和专业的行为、与工作有关的行为、社会责任和客户关系都是你必须考虑的问题。


113 Risk mitigation involves all but which of the following:

A. developing system standards (policies, procedure, responsibility standards)

B. obtaining insurance against loss

C. identification of project risks

D. performing contingent planning

E. developing planning alternatives

正确答案:C


对多项目进行进度计划编制和资源时,以下哪项参数将受到影响?

A、 资源命名用和资源平衡

B、 历时压缩和模拟

C、 活动清单和工作分解结构

D、 进度计划滑动和进行中存货

正确答案:D


项目经理要求项目团队对其项目风险进行量化和评估,以下几点不能证明这样做的好处的是:

A、 彻底理解项目、相关风险、以及风险对项目各部分的影响

B、 制订处理已经识别的问题的风险降低策略

C、 保证所有已以识别的风险问题纳入项目计划编制

D、 识别可能存在的替代方案

正确答案:B


鱼骨图可以帮助

A、 了解过去的结果

B、 组织思维、激发思考

C、 确定过程是否失去控制

D、 对问题进行优先排序

正确答案:B


以下哪项不属于质量管理中使用的根原因分析技术?

A、 鱼骨图

B、 Ishikawa 图

C、 系统或过程流程图

D、 检查清单

正确答案:D


工作分解结构编号系统允许项目员工( )

A.估算WBS元素的成本

B.提供项目论证

C.确定在哪个级别可以找到WBS元素

D.在项目管理软件中使用编码系统

正确答案:C


项目管理师考试题免费下载8篇 第3篇


书面变更命令应该在什么时候需要( )

A.所有的项目,无论大小

B.只有大的项目才需要

C.那些有一个合适的、正式的、范围变更管理系统的项目

D.那些变更控制系统的成本可以调节的项目

正确答案:A


131 Using the table in the Special window, Which task is completed?

A. dig hole

B. remove debris

C. survey

D. set forms

E. place concrete

正确答案:B


在项目的收尾阶段,一系列的行政事物必须得到实施和了结。一个基本的关注就是评估项目的有效程度。成功完成着一任务的一个方法就是( )

A.准备一个业绩报告

B.实施审查

C.进行业绩评价

D.进行采购审核

正确答案:C


A technique that can be used to measure the total income of a project compared to the total moneys expended at any period of time is:

A . return on investment (ROI)

B . net present value (NPV)

C . discounted cash flow (DCF)

D . B and C

E . All of the above.

正确答案:E


89 Feasibility studies evaluate alternatives in terms of

A. Cost-effectiveness

B. Ease of performance

C. Risk

D. Safety

E. All or part of A through D

正确答案:E


Deflection involves the transfer of risk by:

A Contracting out to another party

B Developing schedule alternative.

C Establishing functions under the project manager to handle risk events.

D Disaster planning and responses.

E None of the above.

正确答案:A


在项目做出重要变更时,重要的是要有一个正式的变更过程和一个负责批准或拒绝变更要求的 :

a. 项目相关者

b. 变更控制委员会

c. 领域事务专家

d. 项目经理

正确答案:B


项目管理师考试题免费下载8篇 第4篇


132 The receiver filters messages based on all but the following:

A. Language

B. Distance

C. Culture

D. Knowledge

E. Authority/Reputation

正确答案:B


A project manager can exchange information with the project team using which media?

A tactile

B audio

C olfactory

D visual

E All of the above.

正确答案:E


绩交测量其准是—— ( )

A.PV

B.EV

C.AC

D.ACWS

正确答案:A


78 The Delphi Method is well-suited for:

A. Decision-making

B. Forecasting

C. Overhead rate estimating

D. All of the above

E. A and B only

正确答案:E


在评估限制因素时顾问最初的行动应是 ( )

A.进行概率分析

B.风险识别

C.确定关键资源

D.与项目客户面谈

正确答案:D


7 Using the situation stated in the Special window, what is the total price variance for direct material? A. $140.00

B. $736.00

C. $0.02

D. -$350.00

E. $5850.00

正确答案:B


45 All of the following statements define the role of a meeting chairperson except:

A. Initiates and concludes discussion

B. Controls irrelevant discussion

C. Resolves strong disagreements

D. Produces meeting agenda

E. Consolidates agreements

正确答案:D


项目管理师考试题免费下载8篇 第5篇


6 A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be:

A. 4 weeks

B. 5 weeks

C. 6 weeks

D. 7 weeks

E. None of the above

正确答案:B


60 In a flowchart, the diamond form. is used to represent:

A. a starting point.

B. an operation.

C. a written report.

D. a decision point.

E. an end point

正确答案:D


183 Configuration (baseline) control monitors performance against the

A. scope baseline

B. original schedule

C. original budget

D. All of the above.

E. None of the above

正确答案:A


由谁负责确保讯息清楚明确和完整( )

A.项目经理

B.讯息的发送者

C.讯息的接受者

D.讯息的发送和接受者

正确答案:B


110 The Cost Performance Index (CPI) measures

A. total costs

B. performance over a period of time

C. costs at a point of time

D. variable costs

E. All of the above

正确答案:C


● Which of the following planning considerations is often overlooked?

A Planning for project termination.

B Qualified project manager assignment.

C Insuring top management support.

D Clearly defined tasks.

E All of the above.

正确答案:A


27 Selective perception is _____ of new conflicting information that may result, in a breakdown in communication.

A. Encoding

B. Blocking out

C. Transmission

D. Acceptance

E. Decoding

正确答案:B


项目管理师考试题免费下载8篇 第6篇


● A project can best be defined as:

A Series of non-related activities designed to accomplish single and multiple objectives.

B Coordinated effort of related activities designed to accomplish a goal without a well-established end point.

C Cradle-to-grave activities which must be accomplished in less than one year and consumes human and non-human resources.

D Any undertaking with a definable time frame, well-defined objectives, and consumes both human and non-human resources with certain constraints.

E All of the above.

正确答案:D


● Creation of project objectives:

A allows for data collection and analysis and progress reporting against which standards of performance can be measured.

B is accomplished by selection of measurable variables against which performance can be judged.

C is required before funding of the project by the project sponsor.

D all of the above.

E A and B only

正确答案:E


132 Which of the following is least likely to be used in explaining to a team member why you consider his/her performance substandard?

A. Project office memo

B. counseling session

C. project team meeting

D. formal letter

E. individual conversation

正确答案:C


针对固定价合同,付款的风险是:

A、 承包商的实际成本

B、 承包商的成本加固定费用

C、 在承包商的投标中未公开的应急费用

D、 根据风险评估预测所作的预测成本并用于处理风险

正确答案:C


74 Life cycle costing is the total cost to the customer for the acquisition and ownership over its full life. Life cycle costing categories include the cost of _____, _____, and _____.

A. R & D, maintainability, operation and support.

B. R & D, production, operation and support.

C. Acquisition, operations, maintenance.

D. Production, operations, maintenance.

E. None of the above

正确答案:B


变更请求可能来自:

A、 对项目章程的审核

B、 对执行项目的组织的战略计划的回顾

C、 项目团队解决问题的技能要行以提高

D、 范围定义出错或遗漏

正确答案:D


项目经理通过检查累计成本曲线可以调整( )

A.挣值

B.计划价值

C.成本差异

D.成本绩效指数

正确答案:C


项目管理师考试题免费下载8篇 第7篇


那一类项目成本估算最精确?

a. 初步估算

b. 最终估算

c. 数量级估算

d. 概念估算

正确答案:B
b [见学习手册,评估类型 章节。]


Quality control is normally performed by the _____ .

A . QA personnel

B . project team

C . operating personnel

D . project management

E . None of the above.

正确答案:C


在什么情况下最适合使用Delphi技术?

A、 模似型已完成

B、 拥有丰富的历史资料

C、 规则是启发式的

D、 需要集体知识

正确答案:D


作为一名项目经理,在于员工进行沟通的时候你想要采取移情的聆听方式。在是使用这种方法时,你应该:

A、重复对方所说的话

B、试探对方的意思,然后掂量谈话的内容

C、先评价内容再提出建议

D、站在对方的角度看问题,体验问题

正确答案:D


5 Japanese quality control has improved dramatically in the last 30 years for all of the following reasons except:

A. the use of quality circles.

B. small, continuous improvements in quality control.

C. the use of worker suggestion systems.

D. the use of quality control charts.

E. focusing quality control efforts on production outputs

正确答案:E


● The Work Breakdown Structure (WBS) is the basis for communicating:

A Project scope, cost control, schedule, quality

B Project objectives, dependencies, plan, cost control

C Project scope, schedule, staffing, cost control

D Project scope, quality, schedule, dependencies

E Project budget, schedule, risk factors, work assignments.

正确答案:A


项目章程对项目经理的意义在于( )

A.描述需要完成工作的详细情况

B.说明项目团队成员的名字

C.授权于项目经理

D.描述项目的历史信息

正确答案:C


项目管理师考试题免费下载8篇 第8篇


以下哪一种合同成本可以追溯到某种特定的项目工作上

A、变动成本

B、固定成本

C、间接成本

D、直接成本

正确答案:D


在谈判期间卖方不愿接受买方的合同条款而建议不同的合同条款则卖方使用了哪种谈判技术 ( )

A.评述

B.拒绝报价

C.分割报价

D.反辨counteroffer

正确答案:D


95 A legally binding document offered unilaterally is a _____ .

A. purchase order

B. scope of work description

C. contract stipulation

D. level of effort proposal

E. request for proposal

正确答案:A


了解Halo效应非常重要,因为有这样一种趋势:

A、 内部提拔

B、 聘用最优秀的

C、 把人员调进项目管理层,因为他擅长各自的技术领域

D、 把人员调进项目管理层,因为他接受过项目管理培训

正确答案:C


你的管理阶层要求在项目的每一个阶段要进行一次质量审核。这个审核是如下那一部分的内容( )

A.质量保证进程

B.质量控制进程

C.质量提高进程

D.进程调整计划

正确答案:A


135 A project manager wants to transmit a complex message to several subordinates. What is the best medium by which the manager can get his message across?

A. Oral

B. Written

C. Nonverbal

D. A and B only

E. A, B, and C

正确答案:E


● Using the figure in the Special window, The critical path is:

A A-B-G

B C-G

C C-D

D E-F

E A-B-G and C-D

正确答案:B